ANALYSIS OF THE EFFECTIVENESS OF CRITICAL PATH METHOD IMPLEMENTATION IN FLOOD CONTROL CONSTRUCTION PROJECTS

Authors

  • Andrian Firdaus Yusuf Al Qordhowi Universitas Sunan Giri Surabaya

DOI:

https://doi.org/10.23969/jp.v11i01.44342

Keywords:

Construction management, critical path method, earned value management, time cost performance, river embankment projects

Abstract

Effective control of time and cost performance remains a persistent challenge in river embankment development projects, which are characterized by linear construction processes, environmental uncertainty, and high exposure to schedule disruption. Although construction management techniques such as the Critical Path Method (CPM) and Earned Value Management (EVM) are widely applied, empirical evidence on their integrated effectiveness in flood control infrastructure remains limited. This study aims to evaluate the effectiveness of construction management techniques in controlling time and cost performance in river embankment development projects and to explain the underlying causes of performance deviations. The research adopts a quantitative analytical case study approach, utilizing CPM and EVM to analyze baseline schedules, actual progress, and cost data. The findings reveal persistent schedule delays and moderate cost inefficiencies, with critical activities exerting a dominant influence on overall project performance. Schedule slippage was identified as the primary driver of cost escalation, while the effectiveness of CPM and EVM was constrained by static application and delayed managerial response. The study concludes that construction management techniques are effective as diagnostic tools but require adaptive and integrated implementation to function as proactive control mechanisms. This research contributes theoretically by contextualizing CPM–EVM integration within river embankment projects and practically by providing evidence-based insights for improving time and cost control in flood control infrastructure.

Downloads

Download data is not yet available.

References

Acebes, F., Pereda, M., Poza, D., Pajares, J., & Galan, J. M. (2024). Stochastic Earned Value Analysis Using Monte Carlo Simulation and Statistical Learning Techniques. arXiv. https://arxiv.org/abs/2406.02589

Al Qordhowi, A. F. Y. (2021). Analysis of the Implementation of Bridge Construction Project Risk Management. Enrichment: Journal of Management, 12(1), 957-964.

Al Qordhowi, A. F. Y. (2025). The Use of Agile and Scrum Methods in the Implementation of Advertising Media Construction Projects Reviewed from Time Limitations and Project Locations Adjacent to Cultural Heritage Buildings. Electronic Journal of Education, Social Economics and Technology, 6(1), 663-673.

Chauhan, N. (2025). The role of earned value management in driving cost and schedule performance in engineering projects. International Journal of Research - Granthaalayah, 13(5), 210–227. https://doi.org/10.29121/granthaalayah.v13.i5.2025.6214

Hastomo, A., Anggraheni, E., & Pratama, M. A. (2023). Coastal and river embankment performance under compound hazards conditions. Journal of the Civil Engineering Forum, 9(3), 329–342. https://doi.org/10.22146/jcef.7087

Qordhowi, A. F., & Fendrawan, B. (2025). Analisis efektifitas penerapan Critical Path Method (CPM) pada proyek pembangunan tanggul. Jurnal Teknik Industri Terintegrasi (JUTIN), 8(1), 36105. https://doi.org/10.31004/jutin.v8i1.36105

Rahmadani, L. P., Susanti, J. E., & Dwiyana, P. A. (2024). Cost and time performance evaluation based on earned value analysis method. Journal of Civil Engineering and Planning, 6(1), 10691. https://doi.org/10.37253/jcep.v6i1.10691

Sasmita, A. (2025). Analysis of road and drainage project performance control using the Earned Value Method: A case study of Jakarta Garden City. Eduvest - Journal of Universal Studies,

5(11), 13726–13744. https://doi.org/10.59188/eduvest.v5i11.52275

Pratama, I. D., Nugroho, L. D., & Muhammadun, H. (2025). Measurement of project cost and time efficiency with earned value approach in airport infrastructure projects. Asian Journal of Social and Humanities, 3(4), 478. https://doi.org/10.59888/ajosh.v3i4.478

Puspita, N., & Lutfiansyah, Y. (2025). Cost and time performance analysis with concept of earned value: Case study on Jakarta–Cikampek II elevated project. International Journal of Integrated Education, Engineering and Business, 3(2), 1167. https://doi.org/10.29138/ijieeb.v3i2.1167

Hussein, A. R., & Moradinia, S. F. (2024). Time and cost management in water resources projects utilizing the earned value method. Journal of Studies in Science and Engineering, 4(1), 91–111. https://doi.org/10.53898/josse2024417

Sussendyo, D. J., & Hariani, M. L. (2025). Performance evaluation of urban transportation projects. Journal of Research in Civil Engineering. https://doi.org/10.58466/rigid.v3i2.1878

Soliman, E., Alrasheed, K. A., Alghanim, S., & Morsi, E. (2024). Integrating risk management and earned value framework to detect early warning signs. Journal of Engineering Research. https://doi.org/10.1016/j.jer.2024.05.029

Silitonga, V., Khalifah, V. A. S., & Fansuri, M. H. (2025). Controlling cost and time progress using earned value analysis method for building projects. Journal of Research and Innovation in Civil Engineering As Applied Science (RIGID), 4(2), 1877–1885. https://doi.org/10.58466/rigid.v4i2.1877

Sadeghi, S. (2024). Enhancing project performance forecasting using machine learning techniques. arXiv. https://arxiv.org/abs/2411.17914

Real-Time Data-Driven Construction Project Analysis Framework (2025). RealCONs: Real-time tracking and analysis in construction projects. Automation in Construction.

https://doi.org/10.1016/j.autcon.2025.4045

Topan, R., Tahir Lopa, R., & Bakri, B. (2025). The impact of land acquisition delays on time and cost performance in construction projects: A case study of the Bekasi River Flood Control Project Package 6. Engineering, Technology & Applied Science Research, 15(5), 27400–27405. https://doi.org/10.48084/etasr.13165

Yusuf, A. F. (2025). Evaluation earned value management for teaching time and cost performance in civil engineering education. Global Education Journal, 3(1), 1203. https://doi.org/10.59525/gej.v3i1.1203

Widyarso, R., Witjaksana, B., & Purnama, J. (2025). Analysis of time and cost performance in construction projects using the Earned Value Management method. Asian Journal of Engineering, Social and Health, 4(4), 590–599. https://doi.org/10.46799/ajesh.v4i4.590

Downloads

Published

2026-03-29